Suppose a job contains 3 maintenance tasks. It would be nice (a) to be able to specify the execution order of the tasks; (b) on adding a fourth task, to be able to specify where in the execution sequence it should go. (If this feature is already present, I have not found it yet).
Sponsor
Forum information
Support
2008-06-17T20:17:30Z
Yes, it is present. Open the Job and go to the Task tab. You can change the order there. By default, all Tasks run in order.
Henrik
Support
http://www.visualcron.com 
Please like  VisualCron on facebook!
stanhecht
2008-06-17T21:10:22Z
Thanks. Surprisingly, that control was a little hard to find. Maybe, in the new version, instead of a spinner on the right of the toolbar, two icon-buttons on the left, over the "Order" Column: "<uparrow> Move Up", "<Downarrow> Move down". Or just "Order <spinner>" directly above the "Order" column.