Community forum

Please note that VisualCron support is not actively monitoring this community forum. Please use our contact page for contacting the VisualCron support directly.


Nick Hilder
2016-07-17T06:35:18Z
Hi,
I administer a number of separate databases that in some cases require the same maintenance tasks performed.
So far, I have created a separate group of jobs for each database.
If one of the jobs needs to be updated or a new job added, this needs to be done separately for each group, generally with exactly the same settings and tasks.
In same cases I have been able to use Variables to minimise the amount of changes required for each job.
If there was a way of creating a loop in a job where the current database connection can be selected for each iteration, that would cut down a lot of my time spent maintaining Visual Cron.
Thanks
Kim G
Sponsor
Forum information
Scroll to Top