Community forum

Please note that VisualCron support is not actively monitoring this community forum. Please use our contact page for contacting the VisualCron support directly.


vvenkatasamy
2008-08-01T18:55:53Z

Hi,

I would like to know how to set multiple conditions for a job, like run the job only on Mondays and check if a file is present/created by the previous task/job stream.

Thanks
Venkat
Sponsor
Forum information
Support
2008-08-01T20:42:49Z
To use multiple Conditions is easy. You just have to create a Condition set and add the appropriate conditions. When that is done you need to check the Condition set you want to use in the Conditions tab of the Job. Please read more about Conditions here:

http://www.visualcron.co...dition_sets_and_cond.htm 
Henrik
Support
http://www.visualcron.com 
Please like  VisualCron on facebook!
Scroll to Top