Hello everyone,
I've created a job that needs to be run once an hour. I have set the task inside it to do that.Since I don't need the task to be run just now, but in 2 weeks, I was wondering if there's an option to "pause/suspend" that job for 2 weeks and/or set the start time of the job 2 weeks from now and then run normally once an hour.

To sum up:

I've created a job that I will need to be run once an hour in 2 weeks from now, and want to stop it until then, without checking in 2 weeks to activate it manually.

Regards and thanks in advance,

VC Version: 7.7.3
Sponsor
Forum information
Support
2018-05-16T08:26:23Z
The closest thing to a solution for this is to create a Time exception that lasts for these two weeks and set that Job to use this Time exception.
Henrik
Support
http://www.visualcron.com 
Please like  VisualCron on facebook!
Consulting
2018-05-16T10:34:34Z
Good morning,

Thanks for the quick answer. It seems to be working.
Would you please consider adding a posible future feature to set a start time and end time for the "pause/suspend" option, instead of choosing every year/month/day?

Right Click > Inactivate Job (leave job inactive till user activates it again)
Right Click > Inactivate Job until "select day on calendar" ( leave job inactive until the day selected on the calendar)

Thanks,

Gary_W
2018-05-16T14:49:15Z
Please add your request to the "feature requests" forum. Sounds like a good one!