Community forum

Please note that VisualCron support is not actively monitoring this community forum. Please use our contact page for contacting the VisualCron support directly.


Jeff Hilb
2016-04-08T15:39:36Z
Job runs on server. Job completes. Client running on server shows job completed.

All the clients installed remotely report job is still running.


Sponsor
Forum information
bbusse
2016-04-08T20:15:27Z
Make sure and include the VisualCron Server/Client versions as well as which OS's are in use so when Henrik sees this a better answer can be given.

Brian
Jeff Hilb
2016-04-08T21:48:45Z
Sure. it's Windows Server 2012 R2 running VC 8.0.5 server.

Remote clients are Win 7 running VC client 8.0.5
Support
2016-04-11T10:49:26Z
It is a bug in WMI on some servers (it never gives the response back). You can try the "fallback" option in the Task if that works better.
Henrik
Support
http://www.visualcron.com 
Please like  VisualCron on facebook!
Jeff Hilb
2016-04-26T14:31:05Z
I am running into this on the server side now.

I have a notification setup to report the status of completed jobs. It's reporting the status for the prior job completion, not the one that just ended.
Jeff Hilb
2016-04-26T14:36:16Z
Is the notification considered part of the job? By that I mean, has the current job not really finished if there are notifications associated with it, and that's why it's reporting the result for the prior job execution?

I am using

{JOB(Active|Name)} / {TASK(Active,Name)} - {JOB(Active|Result)}

in the email subject, and receiving My Job / My Notification Name - Failed

where Failed is for the prior job, not the currently executing job